See what is posted, what is committed, and what still needs a forecast.
Entries stay in this browser and are not uploaded. Closing the tab can remove them. Save a draft file to keep your work.
Award financial review · USD
Your review will appear here
Set the dates and complete each category to see the projection.
Work through the example
A positive balance can hide an overrun.
The fictional project has $100,000 authorized, $40,000 posted and $25,000 committed. That leaves $35,000 before other expected costs. Another $40,000 in uncommitted work brings projected costs to $105,000: a $5,000 overrun.
Before changing spending, verify that the $40,000 excludes the existing commitments and check whether the scope, timing or funding assumptions need attention. The calculation identifies a question; it does not authorize a budget change.
Explore the budget-revision lesson preview →Build the reasoning behind the review.
Prepare the award-setup brief, practice a subrecipient-invoice review, or work through MTDC and F&A.
Sources and scope · reviewed September 24, 2026
This original planning worksheet is informed by 2 CFR 200.302 financial-management concepts, Harvard’s reconciliation guidance and Duke’s post-award responsibilities. Institutional practices are examples; the sources do not prescribe this exact forecast or establish its compliance.